MDX PROJECT No.: 83605
|
| OWNER: |
Miami Dade Expressway Authority (MDX)
3790 N.W. 21st Street
Miami, Fl 33142
(305) 637-3277 |
OWNER’S REP: |
Dade Transportation Consultants, Inc. |
| GENERAL CONTRACTOR: |
Community Asphalt Corporation |
SUBCONTRACT AMOUNT: |
$43,714,093.00 |
| CONTRACT TIME: |
1199 Days |
|
| |
 |
GENERAL DESCRIPTION |
The general contract requires the complete design and construction of the SR 836 “Dolphin Expressway” from NW 107th Avenue to NW 137th Avenue Including construction of NW 137th Avenue from SW 8th Street to NW 12th Street, Miami Dade County. Condotte’s subcontract scope of work in this project consists on the construction of nine vehicular bridges, the widening and replacement of traffic railing barrier at two existing bridges over NW 107th Avenue (bridges 14 & 15), ten MSE retaining walls and three Sound Walls. Bridges 1, 2, 3, 6, 7, 8, & 9 are comprised of steel longitudinal box girders; steel cross girders, and flair and circular concrete columns on spread footings. Bridge 13, which spans NW 107th Avenue, consists of precast Florida U-Beams, caps, columns and spread footings. The Bridge at SW 137th Avenue over Tamiami canal consists of a flat slab bridge, caps, and 18” prestressed concrete piles foundation. The Sound Walls consist of a system of precast components assembled over a 30-inch diameter auger cast piles foundation. Temporary components to the project include support of embankments with sheet piles and soil anchors. |
|
|
 |
MAJOR CONSTRUCTION COMPONENTS |
Volume of Concrete |
15,240 CY |
Reinforcing Steel |
3,817,690 LB |
Prestressed Concrete U-Beams |
1,008 LF |
Embankment at MSE Walls |
25,883 CY |
Structural Steel Girders |
15,323,833 LB |
Sound Walls |
190,316 SF |
MSE Walls |
34,875 SF |
18” prestressed concrete piles |
2,290 LF |
|
| |
|
Completion: January, 2007 |
|
|
|