NW 95 STREET TO NW 122 STREET
DADE COUNTY, MIAMI. FLORIDA
OWNER:

FLORIDA DEPARTMENT OF TRANSPORTATION
605 SUWANNEE STREET
TALLAHASSEE, FLORIDA 32399-0450

Ms. Dari Vorce, P.E. 
Phone: (305) 499-2392

OWNERS REP:

BEISWENGER, HOCH & ASSOCIATES
1840 WEST 49 STREET, SUITE 604
HIALEAH, FLORIDA 33012
Mr. Lou Belmonte, P.E.
Phone: (305) 826-2805        
Fax: (305) 826-5446 

STATE CONTRACT NO.:
87260-3589
CONTRACT AMOUNT:
$42,821,001.00
 
GENERAL DESCRIPTION

This project includes construction of 4 bridges, retaining walls, roadway widening, embankments, asphalt paving, road signs, landscaping. Total project length is 2,445 meters.  Construction performed under existing, heavy traffic conditions.

Bridge #1: SR 826 (Palmetto Expressway) over NW 103 Street; total length 70.77 meters, 2 spans

Bridge #2: SR 826 SB Ramp B and NB Ramp B over Little River Canal; total length 25.91 meters,
1 span.

Bridge #3: Ramp D Overpass SR 826; total length 418.35 meters, 11 spans

Bridge #4:  SR 826 over W 60 Street; total length 32.31, 1 span.

 
MAJOR CONSTRUCTION COMPONENTS
Reinforced Concrete
14,224 m3
Structural Steel for bridges
1,234 ton
Pre-cast Concrete Foundation Piles
12,890 m
Temporary Sheet Piling
2,005 m2
Embankment
310,000 m3
Reinforced Earth Panels
31,700 m2
Steel Reinforcements
770,000 kg
AASHTO Pre-cast Girders
3,163 m
Sheet Piling
1,000 m2
Total Bridge Surface Area
1,451 m2
Total Road Asphalt Paving
146,000 m2
 

Completion Date:  August 13, 2002